The London office market is in a “state of suspension” as a result of covid-19 but the number of new projects to break ground in the six months to September was higher than the long-term average.
That’s according to Deloitte’s Crane Survey, which found
that work on 2.6 million sq ft of office space started over the period.
A total of just one million sq ft of central London space
was leased in the three months to September, below the 3.4 million sq ft
recorded in Q3 2019 as the London real estate market entered what Deloitte
called a “state of suspension”.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
There was a 50% decline in the volume of new construction starts
– both new-build and refurbished projects – in central London over the period
but Deloitte said the volume of projects was “broadly in line” with the
long-term average for the survey and the volume of new starts “comfortably
exceeded” new starts in the corresponding period in 2019.
While many speculative schemes had been postponed until
2021, the 35 separate new schemes that broke ground during the period was
higher than the long-term average of 24.
The typical size of a new development shrank by more than a
third on the previous survey and a quarter on the long-term average, however,
amounting to an average of 70,000 sq ft.
The largest new start between April and September was the
447,000 sq ft 20 Ropemaker, which is close to the new Crossrail entrance at
Moorgate station in the heart of the City of London. Demolition work had
already begun in 2019 and the scheme had attracted a 300,000 sq ft pre-let from
Linklaters shortly before the pandemic, leaving only a third of the space
available. This office building is expected to complete in early 2023.
Deloitte said that completion of new office developments was
delayed as contractors worked out how to build safety, holding up planned move.
In the first lockdown, developers were also unable to market buildings as
prospective tenants were unable to visit.
The UK government’s implementation of new restrictions in
England meant that returning to the office has been further delayed but
Deloitte said there was “much hope” that a vaccines programme would provide a
way out of the situation.
Refurbishments on the rise
Meanwhile, there was an increase in refurbishment projects.
The survey found that more than two-thirds of new construction starts involved
an upgrade of existing office stock in as many as 28 separate schemes.
By contrast, just 0.8 million sq ft of new-build construction
started, across seven schemes, between April and September – the lowest figure
in three years. A total of 1.5 million sq ft of new-build new starts has now
been delayed for another few months, while three new-build schemes with a
combined volume of 0.5 million sq ft were paused indefinitely due to market
uncertainty.
Deloitte predicted that with the availability of existing
space in central London rising considerably in the six months to September, there
would be an oversupply of poorer quality workspace. It said it did not expect this
workspace to be absorbed even when the market recovers because occupiers will
look for the best accommodation for their central London hubs.
“In the competitive second-hand market, landlords will
increasingly need to improve and refurbish their existing office stock to the
highest standards to be able to attract tenant demand and maintain the value of
their buildings. The ‘flight to quality’ is therefore likely to become more
pronounced, with more emphasis on sustainable, ‘healthy’ and ‘WELL’ buildings,”
it predicted.