Balfour Beatty Vinci installs huge gantry crane to lay HS2 prefab slabs

HS2 Curzon Approaches Image: HS2
Aerial view of the gantry being craned into position. Image: HS2

A 125-tonne gantry crane has been lifted into position to lay prefabricated slabs as part of the HS2 approaches to Birmingham city centre.

Contractor Balfour Beatty Vinci (BBV) has spent four years manufacturing 2,742 concrete segments for the Delta Junction at a purpose-built factory in Kingsbury, Warwickshire.

These will form five interconnected viaducts which make up the approaches to the line’s Curzon stations.

HS2 Curzon Approaches Image: HS2
The gantry crane will lay slabs for the HS2 Curzon approaches. Image: HS2

The operation will take 18 months, with the crane laying the slabs one at a time as it works its way from Lawley Middleway viaduct to Curzon 2, Curzon 1 and finally Duddeston Junction viaduct.

HS2 Curzon Approaches head of delivery Greg Sugden said: “This is a huge moment for the Curzon approaches team, as we begin what is essentially the last major phase of civil engineering works on this section of the route.

“It’s a test of skill and precision, as we must ensure that when the gantry crane arrives at each structure, we’re ready for the deck installation works to begin.”

Image: HS2
Team members view the gantry being positioned. Image: HS2