Contractor Sir Robert McAlpine is progressing the decarbonisation of Port Talbot’s steelworks in Wales with the first significant concrete pour.
Earlier this month, the firm poured 800 cu m of concrete to support the base of what will be the new fume extraction plant’s chimney stack. The firm is working with Toureen Group on the scheme.
In a LinkedIn post, the firm said the operation involved a continuous, 18-hour pour at a rate of rise above 600mm per hour, with concrete supplied from local batching plants in the Port Talbot area.

This required temporary works to secure the 2.4 m-long holding-down bolts, helping to form the securing crown which will hold the chimney stack in position.
The fume extraction plant will capture, filter and provide a safe means of collecting airborne particulates generated from the new electric arc furnace when in operation.
Elsewhere on site, a piling programme continues for the infrastructure needed to support the future of green steelmaking, including for the new primary pump house, which will feed water from the lagoon into the steel plant and rolling mills.
Work to infill part of the lagoon – creating more room to build – is now complete, with an estimated 160,000 cu m of suitable fill material used overall and the banks of the lagoon lined with riprap protection material.