Gateway 2 applications plummet post Building Safety Levy launch

The latest building control gateway 2 update from the Building Safety Regulator (BSR) shows a continuing de-gumming of this new and complex process. The 12 weeks to 30 May saw an increase in approval rates across all categories of applications, including existing building safety projects, after it introduced an external remediation improvement plan in April. The plan introduced a new external remediation multidisciplinary team to mirror the Innovation Unit (IU) set up last September. This streamlines communication and processing through dedicated account managers. It also saw a recruitment drive to cut individual caseloads from an average of 25 down to around 10. For new builds, IU decisions overtook the number of new cases received in the period. Across all categories, BSR made 358 gateway 2 decisions, with a 75% approval rate. 65% of all decisions related to London cases. Applications representing 14,928 units were determined, of which 9,499 (64%) were approvals. There are currently 38,775 residential units in live cases. New applications for 13,964 units came in during the period. External remediation approvals up The IU approved 90% of cases – 28 out of 31 – in the period. London saw a 100% approval rate for its 19 case decisions. The regulator said this reflects the extra engagement with applicants. All-time IU approvals now stand at 43, with a median approval time of 22 weeks. The IU is currently managing 131 applications, representing 30,369 units. On external remediation, approval rates rose to 79% over the last 12 weeks, well above the minimum 65% end of year target for 2026. BSR credits operational improvements and intensive work to improve quality of applications. Currently, 16 legacy remediation applications from 2024 remain. A further 10 are on track to be determined in June. This is down from 42 outstanding at the beginning of 2026. BSR said the data show that 2026 applications are progressing faster than before. The average approval time is still 39 weeks in a rolling 12-week period, but BSR said this was “being skewed by our focus on closing out the older 2024/2025 applications”. People still waiting “We continue to see positive improvements in numbers of approvals for both new build and existing building remediation cases, as well as significantly faster decision times,” said acting BSR chief executive Charlie Pugsley. “This includes continued positive results from our Innovation Unit by working closely with applicants to safely resolve complex technical challenges. This positive engagement has seen a growing number of decisions and rising approval rates.” He added: “However, we recognise that people living in other unremediated buildings still want them to be fixed safely, and at pace.”

Gateway 2 applications for high-risk buildings (HRBs) plummeted in October following the introduction of the Building Safety Levy, new figures have shown.

Data published this week by the Building Safety Regulator (BSR) shows there were only six applications in October after the levy was introduced at the start of the month – this compares with 60 applications in September.

The BSR report – which covers the three months from August to October – also showed there was a late surge of 41 applications after 21 September, but of these eight were recommended for rejection and 18 were poor quality.

The BSR is implementing a five-stage approach to handling the surge of applications from prioritising certain types of applications to triaging different quality applications and detailed assessments.

The levy is part of the Building Safety Act 2022 and aims to raise an estimated £3.4bn toward the government’s historical building safety and cladding remediation programmes. It applies to major developments of more than 10 dwellings or 30 student beds.

The overall process has faced some industry criticism and concern. Speaking at the London Build event this week, Supervene Architects director Alex Taylor said whilst he was a “big believer” in the overall objectives of the gateway process “it’s being administered in the wrong way”.

Taylor added that he was concerned about resources at the BSR to handle the surge – in particular in dealing with the move from HRBs moving from gateway 2 to gateway 3. “Resource is a problem. It’s a barrier,” he said.

Taylor said there were also wider concerns in the sector over viability of projects which was impacting on architects, many of who whom are struggling financially.

Earlier this month leading practice Levitt Bernstein applied for a company voluntary arrangement (CVA) and cut jobs. Taylor said architects were a “canary in the coalmine” of wider economic issues facing the sector.

Story for CM? Get in touch via email: [email protected]