- Gold winner: Massimiliano Crea MCIOB
- Mid Group
- Project: Stonebridge Primary School, London NW10
- Scope: Construction of new teaching block and hall, and refurbishment of Grade II-listed building, completed in 67 weeks
- Client: London Borough of Brent
- Contract: JCT D&B
- Value: £7.5m

Massi Crea’s design input at the start of the Stonebridge Primary School project was responsible for significant cost savings.
He changed the building layout, placing classrooms on the perimeter of the existing building, to equalise the air conditioning requirement, then equipped each one with its own standalone natural ventilation and heat recovery unit, reducing the amount of expensive duct work required.
The steel frame of the new build, which required lengthy lead-in times, was replaced with timber structural insulated panels, which could be installed from smaller mobile cranes, and speeded up the programme. Crea also removed the new block’s projected second storey, relocating the classroom spaces to the existing building’s old hall as part of the refurbishment programme.
These changes slashed the budget by £1.2m and despite the redesign work enforcing a late start on site, Crea still handed over five months early.
Register for free or sign in to continue reading
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.