Understanding the three main economic metrics underpinning construction is vital during uncertain market conditions, says Pablo Cristi Worm

A common assumption is that increases in input costs translate directly into higher tender prices and that construction costs and tender prices move in parallel. I often receive questions like, “If the National Living Wage is increasing by 3.9%, how much are tender prices increasing?” However, costs and prices frequently diverge, driven by shifts in market capacity, contractor pricing behaviour, profit margin adjustments and complex supply chain dynamics.
Evaluating inflation within the built environment requires a clear distinction between three core economic measures that are frequently conflated in commercial discussions. Each metric tracks a different stage of the construction pricing cycle and serves a distinct analytical purpose.
The first, building cost indices, measures changes in the direct input costs incurred by contractors to deliver a project. Indices such as the General Building Cost Index (GBCI) produced by the Building Cost Information Service (BCIS) or the Aecom Building Cost Index (BCI) track prices paid for materials, labour and plant equipment.
There’s no need to list the extensive inflationary shocks that have affected building costs in recent years. These pressures have shifted from rapid commodity price spikes to persistent structural pressures that have set a higher cost baseline. More recently, rising labour rates and regulatory compliance mandates have driven this shift.
The BCIS Labour Cost Index spiked 7.7% in the year to Q1 2024 and has maintained an annual average growth of 3.8% through Q3 2026. Structural demographic challenges and legislative adjustments have driven this persistent level. Successive increases in the National Living Wage have raised baseline wages, while continued skill shortages, exacerbated by trade retirements and constrained domestic training pipelines, have forced contractors to pay premium salaries to secure site workforce.
Volatile component costs
Another key driver of input cost inflation is materials and building components. However, these tend to be more volatile across specific trade categories, with prices rising and falling sharply due to economic shocks and supply-chain disruptions. For instance, steel has had the most challenging few months of any construction material, and not only because of the conflict in the Middle East affecting energy-intensive materials.
The EU Carbon Border Adjustment Mechanism (CBAM) implementation in January 2026, UK import tariffs in July 2026, and the upcoming UK CBAM are all loading inflationary pressure on steel prices. More generally, over the past 10 years, material prices have reached disinflation territory twice: at the start of 2020, and during the second half of 2023 and the beginning of 2024.

Tender prices
The second measure, tender price indices (TPI), tracks the price levels of accepted tenders submitted by main contractors to execute projects for clients. Indices such as the BCIS All-in TPI or the Aecom TPI measure work items from competitive tenders to establish market price movements over time.
The principal driver of tender price inflation is the balance between construction market demand and contractor capacity. When order books are full and future work pipelines are robust, as in 2021 and 2022, contractors become selective, elevating tender prices to expand profit margins and directly passing on any input cost increases to clients.
Conversely, when market demand weakens, or project starts are delayed, as has been the case since 2023, contractors compete aggressively for well-designed schemes and cut prices to win jobs. Under these soft market conditions, contractors frequently squeeze margins and absorb input cost increases to maintain site turnover and avoid an idle workforce, resulting in subdued tender price inflation even during periods of elevated resource costs.
The often overlooked measure – output prices
The third measure, and one that often gets overlooked, is the Construction Output Price Index (COPI) produced by the Office for National Statistics (ONS). This records the aggregate prices clients actually pay for completed work across both new construction and the repair and maintenance sectors. While COPI provides a backwards-looking measure of total sector price movement, tender price indices serve as forward-looking indicators of current bidding behaviour and future project commitments.

The interaction between costs and prices is non-linear, delayed, and heavily shaped by macroeconomic conditions, market competition, contractor risk appetite and investor confidence. 2026 data provides evidence of this structural decoupling. Between Q1 and Q3 2026, the BCIS GBCI rose 3.9%, while BCIS All-in TPI rose 1.7%. During the same period, the ONS COPI increased by 3.2%.
“Today’s market is unusually cheap to buy in. That is a window, not a new normal.”
This divergence is due to a combination of developers delaying investment decisions until project viability improves, contractors finding it hard to pass the full impact of input cost inflation on to clients, and multi-tiered supply chains delaying price pass-through. Raw commodity price spikes, such as movements in global iron ore, copper, or crude oil, do not immediately alter tender rates on project sites.
Intermediate manufacturers, stockholders and sub-tier trade contractors often absorb initial volatility through fixed-price supply agreements or inventory reserves. When demand is subdued, and order books are thin, tender prices only react after input cost changes persist long enough to force supply contract resets.
Protect viability whilst being competitive
The divergence between construction costs and tender prices creates both opportunities and risks for the industry.
For clients and developers, competitive tender prices may provide an opportunity to secure projects at relatively favourable prices. Today’s market is unusually cheap to buy in. That is a window, not a new normal. Lower tender price inflation should not automatically be interpreted as evidence that project costs will remain stable.
Clients can engage with main contractors early during design development to improve buildability and cost certainty, and adopting balanced procurement models and flexible price fluctuation clauses, rather than forcing fixed-price arrangements onto bidding contractors, could help to avoid disputes or insolvencies.
For contractors and the supply chain, the challenge is to protect commercial viability while remaining competitive. If input costs continue increasing but tender prices remain subdued, profit margins and financial resilience may come under pressure. In the current climate, it is even more important to practice disciplined project selection and risk profiling rather than simply cutting prices to win turnover.
Pablo Cristi Worm is construction economist at Aecom