The HS2 high-speed rail project has begun its search for specialist contractors to design and build 280km of high-speed slab track between London, Birmingham and Crewe.
The winners will also take a lead role in managing and coordinating the complex interfaces between the track and other elements of the rail systems.
Contracts covering rail, switches and crossings and pre-cast slab track systems will be awarded separately – with the track systems suppliers coordinating the design and installation.
The winning bidders are set to arrive on site once the tunnels, bridges, viaducts and earthworks are complete.
Six more sets of rail systems contracts are due to be launched later in the year, covering signalling, the overhead catenary that will provide power to the trains, mechanical and electrical systems, high voltage power supplies, communications systems and the depot and control centre at Washwood Heath in Birmingham.
Four separate track packages will be awarded:
- Lot 1 – Phase One (Urban – London and Birmingham) – £434m
- Lot 2 – Phase One (Open Route – Central) – £526m
- Lot 3 – Phase One (Open Route -North) – £566m
- Lot 4 – Track – Phase 2a – £431m
In order to reduce long term costs and improve performance, the track will be set onto concrete slabs instead of the ballast commonly used on the UK rail network. This approach – known as slab track – is commonly used on metro systems and some international high-speed rail lines.
The winning bidders will also be responsible for the design, installation and testing of switches and crossings, managing construction logistics and co-ordination, and supporting the testing and commissioning phase. They will also act as Construction Design and Management (CDM) Principal Contractor for the trace and be responsible for logistics and consents co-ordination.
Shortlists for track are expected towards the end of the year, with contract awards in 2022.
HS2 Ltd’s procurement and commercial director, David Poole said: “Rail systems are some of the most important parts of the HS2 project – the high tech equipment and systems that will allow our trains to deliver an unparalleled service in terms of speed, frequency and reliability.
“The launch of this new procurement contest is an important milestone for the project, and a significant opportunity for the industry and the wider supply chain. At the peak of construction, HS2 will support around 30,000 jobs and contracts like this will provide a real boost for employers across the supply chain, helping to boost skills and provide opportunities for years to come.”