Video

Video | Striking footage shows progress at Hinkley Point C

A new video shows Hinkley Point C’s progress as teams at the new nuclear power station get ready to lift the domed roof onto the second reactor building this summer.

The footage shows that construction of Unit 1’s buildings is almost complete, as the installation of equipment advances inside.

Meanwhile, the second unit, which was stopped during the pandemic, is catching up with its 245-tonne dome due to be lifted over the summer. This will allow it to move into its fit-out phase.

Story for CM? Get in touch via email: [email protected]

Leave a comment

Your email address will not be published. Required fields are marked *

Latest articles in Video