Video | 8,000t cantilever hoisted into place
https://youtu.be/TbMfFqoKR9A
An 8,000t tonne, 227m-long cantilever whose structural steel weighs more than the iron in the Eiffel Tower, has been lifted into place to join together two towers in Dubai.
The Link forms part of develop Ithra Dubai’s “One Za’abeel”
mixed-use project in Dubai.
Main contractor Alec Engineering and Contracting embraced 4D
modelling with Bentley’s Synchro for the project, which it was claimed knocked
70 days off the programme and saved £12.5m.
One Za’abeel comprises two tall podium-mounted towers on
either side of a busy thoroughfare, next to the Dubai World Trade Center
Exhibition Halls. The towers are now linked 105m up by a steel bridge which
juts 66m into thin air. The link itself is 227m in length, a horizontal
skyscraper in its own right.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
The main bridge section was constructed at podium level while the towers were being built and, as its length grew, Alec slid it in scheduled movements across the busy road. It was strand-jacked into place as part of the largest lift to date in the Middle East. The bridge structure will be finished as an interior space with an infinity pool on its roof.
Dr. Fadi Jabri, executive officer at Japaenese architecture
firm Nikken Sekkei, which was responsible for the concept and design of the two-tower
structure and the cantilever said: “Designing the world's longest-occupied cantilevered
building was an ambitious challenge in itself. However, designing an offset
cantilever between two towers, 100 metres above a busy highway, was a challenge
of ingenuity and imagination none of us had ever faced before."
"The lifting process was incredible. The
initial lift on the 18th August was a mere ten centimetres to check
for cable stretching and the building's reaction to the strain – all
works will be halted so we could listen to how the building would react. A further one metre lift
took place a week later, followed by the main
event, three days later – the final 100 metre lift into
place.”
The CM March 2026 issue of Construction Management magazine is now available to read in digital format.
Powered Access
CM, in partnership with IPAF, has launched a new survey to explore the industry’s views and experiences with powered access machines on construction projects.
This is not a first step towards a paywall. We need readers to register with us to help sustain creation of quality editorial content on Construction Management. Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings. Thank you.