The £14m benefit of using AI-enabled scheduling
CM Digital Staff
Image: Nodes & Links
Major project consultancy Herne Group has generated £14m in ‘acceleration value’ after using AI-enabled scheduling from Nodes & Links on its projects.
On one particular defence project, a client-instructed scope change put a fixed completion deadline at risk. Herne used the Nodes & Links platform to identify and test recovery options, substantiate its recommendations and agree changes with the client. The work supported eight weeks of recovery and more than £4m in acceleration-related savings.
The client’s change pushed the forecast completion date beyond the date required for an asset of national importance. Herne had to accommodate the additional scope without moving that deadline.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
A 1,000-iteration probabilistic risk analysis in Nodes & Links put the probability of achieving the planned completion date at just 0.2%. With slippage costing around £80,000 a day, Herne needed to establish which interventions could recover time, what they would require and whether they were practical to deliver.
The challenge for Herne was not a shortage of schedule or risk data, it was turning that information into a defensible recovery plan before the window to act narrowed further. Herne needed to investigate alternatives, understand their effect on completion and give senior management and the client sufficient evidence to authorise changes.
Where intervention makes a difference
Herne asked Nodes & Links a direct question about its live schedule: now that the completion date has slipped, what options are available to recover it?
The platform identified and modelled interventions including extended working hours, fast-tracking, changes to schedule logic, earlier completion of documentation and resequencing activities. The initial analysis identified scenarios offering up to 39 calendar days of potential recovery.
This gave Herne a basis for comparing options before committing resources or seeking client approval. The team could see the modelled effect of each intervention on the completion forecast and focus on the measures with the greatest recovery potential. Herne’s project team then assessed the options against resource availability, cost, sequencing constraints and client requirements.
At that stage, the highest-impact option identified was to move selected critical commissioning activities from a five-day to a seven-day working week. Herne used the supporting evidence to take the proposal to the client, secure agreement and implement the change. Further analysis identified additional interventions, which Herne assessed and incorporated where feasible.
Herne project controls director Andy Garnett said: “There is no other software out there that allows us to interrogate a live programme in this way and quickly identify where intervention is possible, where delivery performance can be improved, and where recovery and acceleration opportunities genuinely exist. It is truly helping us recover slippage and accelerate key milestones.”
Not a one-off exercise
Recovery was not a one-off exercise. At each schedule update, Herne used Nodes & Links to assess the effect of measures already implemented and identify further opportunities as the work progressed. This kept recovery decisions tied to the current delivery position rather than a plan developed against an earlier schedule. Each update gave the team a revised view of the completion forecast, the effect of its interventions and the options still available.
The auditable reasoning behind the recommendations helped Herne explain and defend its decisions to senior management, the client and assurance reviewers.
By the next schedule update, the measures Herne had implemented had delivered 15 days of improvement. Within three months, the P50 completion forecast had moved forward by 10 weeks.
Herne is using Nodes & Links on its other projects, generating a total of £14m in acceleration value.
“Herne are a perfect example of where project controls is heading,” said Nodes & Links CEO and co-founder Greg Lawton. “They are combining deep delivery expertise with auditable AI to investigate more options, understand the consequences and turn insight into practical action on live, high-stakes programmes.”
Other companies, including Aecom, Galliford Try Highways and BAM, have also used Nodes & Links’ AI-powered schedule management platform. In 2022, Nodes & Links was one of two UK startups among 10 chosen by Vinci to receive support from its Catalyst programme. It also featured on the Cemex Ventures’ Top 50 ConTech Startups list for 2021.