A serious fire may result in more serious consequences in a modular building, new research backed by the Ministry of Housing, Communities and Local Government shows.
While there is not enough evidence to suggest whether a fire is more or less likely in a volumetric construction compared with traditional building methods, the Harlow Consulting and Edinburgh Napier University joint study found the consequences could be worse if combustible elements are used in the voids and cavities through which fire and smoke can travel quickly.
Previous studies have already identified a conflict between sustainable building design and fire safety compliance.
“Evidence from respondent interviews suggests it is easier to demonstrate sustainability credentials within volumetric construction, compared with traditional construction,” said the document.
“Furthermore, combustibility concerns about the use of timber can lead to increased use of materials such as concrete, undermining potential for embodied carbon savings.”
Gaps in regulatory framework
Researchers say fire performance and the requirements particular to modular construction must be well understood from the outset and factored into the design to mitigate these risks.
It added: "Risks can be introduced if there is no fit-for-purpose fire strategy, in the event of lack of continuity of structural and general fire engineering expertise throughout the project and where standard fire testing does not work effectively for volumetric products and systems."
It added that respondents to the research broadly agreed that there are gaps in the regulatory framework concerning volumetric construction.
The research was published in the context of the government’s commitment to support MMC and to investigate potential risks to safety and performance posed by volumetric construction and identify potential options for mitigating those risks.
I can not see how the fire performance is much different to timber framed houses, which have been built in their millions? Surely the regulatory framework is the same, requiring appropriate fire breaks and a minimum performance in walls of either half or one hour. I guess the key is compliance with these regs, which based on recent cases is not there?