Project: Morgan Sindall gets ahead of the curve

Morgan Sindall’s Laura Allison describes a school build which involved multi-stakeholder engagement and a challenging curved design.

We were appointed by North Lanark-shire Council through its Schools and Centres 21 framework to design and build a new £17m primary school which would allow two existing schools to come together in a modern, spacious learning environment. 

Split into three phases, the 484-capacity Hilltop Primary School was delivered as a tandem build, in field space alongside the existing Dunrobin Primary, to accommodate its pupils and those of the nearby Petersburn Primary.

Early and collaborative stakeholder and community engagement was particularly crucial. We were acutely aware that we, with the council and the schools, were not only constructing a new building, but a new school, with an original name, crest, uniform and identity. There was an additional dynamic: one set of pupils and teachers would be relocating to a site where there was already an existing cohort. 

Register for free or sign in to continue reading

This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.

Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.

Story for CM? Get in touch via email: [email protected]

Latest articles in Technical