Technical

Madeira Terrace: Restoring Brighton’s cast iron icon

It’s believed to be the longest cast iron structure in Europe. Kristina Smith visits the Victorian-era Madeira Terrace in Brighton, where a painstaking heritage project is under way

One of the restored cast iron arches in the Madeira Terrace. Image: JT Mackley
One of the restored cast iron arches in the Madeira Terrace. Image: JT Mackley

Outside Brighton’s outdoor beachside swimming pool, Sea Lanes, two people are pointing to something across the road, chatting intently. It is the first section of a rejuvenated Victorian cast iron structure, Phase One of the ambitious Madeira Terrace Restoration project.

Designed to provide a covered promenade and a walkway on its deck, the terrace stretches for 151 arches – or 865m – along the east end of the city’s seafront. Supported on the cliff face at the back, and on columns at the front, the deck sits halfway down the cliff with Marine Parade, the A259, above and Madeira Drive and Brighton Beach below.

Contractor JT Mackley & Co has the £12.1m contract to restore 28 arches between the Madeira Shelter Hall, home to music venue and nightclub Concorde 2, and the Royal Crescent steps. The project includes works to the east cliff wall, the installation of a new lift and a new staircase by Concorde 2.

The restoration of the Grade II*-listed structure is a painstaking process, driven by a heritage-first approach. Mackley must carefully dismantle the structure, sending each of the 26 pieces that make up each bay to a specialist foundry to be cleaned, inspected, repaired where necessary, and repainted before being returned and assembled in their original position – with a rigorous testing regime woven in.

Madeira Terrace Restoration Phase One

  • Client: Brighton & Hove City Council
  • Project manager: AtkinsRéalis
  • Architect: Purcell
  • Civil, and structural engineer: HOP
  • Conservation Engineers: The Morton Partnership
  • M&E design: Stantec
  • Landscape architects: Landscape Projects
  • Cost consultant: MGAC
  • Business planning: Fourth Street
  • Contractor: JT Mackley & Co
  • Construction cost at tender award: £12.1m
  • Form of contract: JCT Standard Building Contract Without Quantities
  • On site: November 2024 to Winter 2026

Main subcontractors

  • Cast Iron restoration: Cast Iron Welding Services (CIWS)
  • Cast Iron Load Testing – Mann Williams
  • Piling: Green Piling
  • Sprayed Concrete: Shotcrete Services
  • Brickwork: K & T
  • Copper roofing: Eco Roofing
  • Lift: Lift Design
  • Mechanical and electrical: Simpson Electrical
  • New Cast Iron: FSE
  • Concrete Works: WestConn

“We are working with a material that there isn’t a huge amount of knowledge about out there,” says Brighton & Hove City Council’s programme manager Ian Graham. “How do we garner that knowledge and that expertise? And how do we apply modern design standards? That has been the big technical challenge for us.”

Mackley, which started on site in October 2024, is a civil engineering contractor, which specialises in coastal projects. It has a track record with cast iron structures, delivering the maintenance contract for Worthing Pier and having worked on Eastbourne and Brighton Piers.

But this is a one-off. “It is totally different from anything I have done before,” says Mackley’s contracts manager Mike Clegg, who has almost 40 years’ experience across varied civil engineering projects. “Everything is a learning curve. It’s about finding the best way to do it and then getting it done.”

Although the project is being delivered under a traditional form of contract, JCT Standard Building Contract Without Quantities, Mackley and the design team have worked together to refine many of the details, explains Keith Brownrigg, senior project manager for AtkinsRéalis which is project manager for the scheme.

“It’s been a collaborative approach. We have been fortunate to have JT Mackley on the project because they have been proactive in engaging with the design, challenging the design team, ensuring that what’s getting built is suitable.”

The Madeira Terrace prior to work starting. Image: JT Mackley
The Madeira Terrace prior to work starting. Image: JT Mackley

A unique structure

Believed to be the longest cast iron structure of its kind in Europe – possibly in the world – Madeira Terrace was built in two sections, between 1889 and 1897. Becoming progressively unsafe due to the deteriorating condition of the structure, the whole area has been behind a security fence since 2015.

The length being restored under Phase One sits within the older section, with that portion chosen to optimise movement between Marine Parade and the beachfront, explains the council’s project manager Abigail Hone.

“With the design team, which came on board in early 2020, we were looking at the hinterland of the Terrace, and what was happening development wise on the sea side,” they say. “We looked at how people get here, what were the dominant pedestrian routes.”

The striking new lift, designed to acknowledge, but not mimic, the Victorian Madeira Shelter Hall lift – in need of costly repairs and not in use – is a vital part of the scheme, opening up access to the seafront for people using mobility scooters and prams. “Accessibility is hugely important to Historic England,” notes Graham. “Without the lift, we probably wouldn’t have got their investment.”

“It’s been a collaborative approach. We have been fortunate to have JT Mackley on the project because they have been proactive in engaging with the design”

Keith Brownrigg, AtkinsRéalis

Historic England has provided £750,000 funding towards the restoration, with £500,000 coming from a 2017 crowd-funding campaign, boasting backers including Fat Boy Slim, Suzy Eddie Izzard and Damon Hill. The council allocated over £10m including £300,000 from a carbon neutral fund – justified by the extensive reuse of the cast iron. Original plans for Phase One encompassed 40 arches and the refurbishment of Royal Crescent steps, but inflationary pressures forced the council to reduce the scope, says Graham.

Mackley’s contract includes works to stabilise the original east cliff wall, reinforced by the Victorians in the 1830s with a mixture of stone, brick and render, a Brighton-specific material known as bungaroosh. This became the Green Wall – much loved by local residents – after the Victorians introduced Japanese Spindle plants in 1872, pre-dating the Terrace.

One section of the Green Wall in Phase One has remained intact, without works to the bungaroosh; an experiment, explains Graham. The rejuvenated sections will be greened with new plants, grown from the base of the wall onto trellises fixed to the new concrete face.

A retained section of the Green Wall, showing the cast iron corbels
A retained section of the Green Wall, showing the cast iron corbels. Image: Kristina Smith

Careful disassembly

Mackley started on site in November 2024, removing asbestos from joints in the wall and deck, taking down most of the Japanese Spindles and other plants that had colonised the wall and clearing the site. The site compound is small, with most materials stored offsite.

Having removed lead paint from the joints in the cast iron structure, Mackley began the careful dismantling of the arches in February 2025. Cast Iron Welding Services (CIWS), the foundry tasked with restoring the cast iron elements, were on site to advise the team who were all direct Mackley employees, to ensure close control of the delicate operation, says Clegg.

CIWS had carried out earlier investigative works on the cast iron for the Council, although the choice of foundry was left to Mackley. “On visiting them and seeing that they had a good understanding of the project and of what was involved, I took the decision to work with them,” says Clegg.

Starting with the careful munching of the concrete deck, from the middle outwards to limit vibration in the cast iron, the dismantling process saw Mackley’s team label, measure, weigh and test every element with a magnet – as some have been replaced by aluminium over the years. All information is recorded on an app developed within the Procore platform.

“We are working with a material that there isn’t a huge amount of knowledge about”

Ian Graham, Brighton & Hove City Council

The initial assumption was that some of the cast iron pieces will require no repair work at all, others will have cracks that CIWS will repair using gas fusion welding, a few may need recasting altogether. With its knowledge of cast iron, and of this particular structure, CIWS agreed to a fixed price contract.

“The main pressure on price for them is the balance between recasting and repair,” comments Graham. Recasting requires raw material and far higher temperatures, whereas repair requires skilled work that is labour intensive.  

The worst case so far, says Clegg, was one of the spandrels which had 26 breaks in it. With a few elements yet to be processed, none had needed recasting by mid-April, a process which takes 26 weeks and hence could yet have a knock-on effect to the overall programme.

One of the restored masks. Image: JT Mackley
One of the restored masks. Image: JT Mackley

After CIWS receive the cast iron elements at their Coalville facility, they grit blast each item, spray them with white paint, check measurements and mark up where repair is needed. Looking at a photo of one of the masks that sit either side of the keystone – believed to be Aphrodite and Poseidon – the metal could have been cast yesterday.

It’s hard to believe these are the same pieces on view in the existing structure. Hone explains that it is the wrought iron bolts that have rusted and expanded, causing fractures in some elements as well as extensive staining. Layers of paint – up to 28 in places – further distort the shapes and lines.

Structural engineer HOP has had the difficult task of proving CIWS’ confidence in the cast iron. They have worked collaboratively with conservation engineers The Morton Partnership and Mann Williams to develop a robust testing regime.

“HOP has had to build a unique structural model and prove by first principles that it stands up,” says Dave Mills, regional director at AtkinsRéalis. The deployment of innovative techniques, such as the non-intrusive dynamic testing, have proved invaluable in identifying issues and building confidence in the original century old cast iron.

In a process that has evolved, all the items undergo dynamic testing, with some subject to compression and tensile testing. Before they can be re-erected live load testing takes place; elements for the first six bays have been fully tested, explains Clegg, moving to 50%, 20% and 15% as the project progresses.

“The testing regime has been more intensive than we expected to prove we can safely reuse,” says Graham. “It’s tricky… we have got to get it right, but it’s getting that balance.”

Surprises

There have been plenty of other issues to be addressed at monthly meetings with the design team, and Mackley’s six-person in-house technical services team has fed into the process.

“It is totally different from anything I have done before. Everything is a learning curve”

Mike Clegg, JT Mackley

Super-hard flints in the bungaroosh mean that coring through it has been impossible. The project team has had to devise new ways of installing steel bars into the cliff wall, and new ways to validate their capacity. Some of these will support the new terrace deck, some will hold trellises and some are for a reinforcing mesh below new layers of structural concrete.

The surprising resilience of the bungaroosh and the decision to pin rather than remove historic repairs has led to welcome savings. With a point cloud survey, Mackley discovered that the original wall had receded less than expected. Working with contractor Shotcrete Services, the new approach required less sprayed concrete.

Mackley also discovered, during dismantling, that the cast iron corbels set into the cliff to support the structure were not as the original Victorian drawings suggest; they have an additional fin that sticks into the wall, which meant that Mackley had to adapt the installation sequence.

CV: Mike Clegg, contracts manager, JT Mackley & Co

Partly inspired by his older sister studying civil engineering, Mike Clegg took an aptitude test at 16 with the CITB and was offered a management course at Bircham Newton. JT Mackley sponsored him through an ONC and then employed him while he completed an HNC.

Progressing from chain boy to site manager by his early 20s, Clegg spent nine years with Mackley followed by several career moves – “the opportunities came along” – and management roles in projects and frameworks across rail, airports, water, highways and sea defences. In August 2023, another call from a recruitment agency led him back to Mackley.

“I enjoy mechanical ideas, turning drawings into something that works,” says Clegg. “I could not be doing a job where I was working in an office every day.”

Re-erecting the first of the rejuvenated bays has also added to the ‘lesson learned’ list. The introduction of new steel elements – the front beam and a key stone on which the masks will be hung – caused tolerance headaches for Mackley.

“The columns are not straight; they are like bananas. But we don’t know which way they bend until we are erecting them, so the spandrels don’t quite align,” explains Clegg. The solution has been to elongate the bolt holes in the new steel beams.

Mills notes that the designers have devised details to separate cast iron and steel at joints, to avoid any risk of bi-metallic corrosion. “We are building back better,” says Graham.

Given the complexities of restoring the Victorian structure, it is perhaps surprising to learn that the construction of the lift shaft has caused the most co-ordination headaches. “It has been one of the most complex parts, design wise,” says Hone.

Clad in four types of brick – two red, a black glazed header and glass – which have been laid with lime mortar, the shaft is a steel-framed structure founded on continuous flight auger (CFA) piles with the lift operated by a pneumatic ram housed in a plant room at the lowest level. Steel lintels, clad with brick slips, transfer the load from the brick wall to the steel frame at four points.

“Getting the steel frame, brickwork, lift, heritage, mechanical and electrical parties all to talk to each other and get everything coordinated has been a real challenge,” says Mills. “It has been an iterative process; you solve one problem and create another.”

By mid-April, the lift shaft structure was well advanced with the brickwork almost complete and a bridge between the lift and pavement at the upper level in place. The copper roof installation was about to start, followed by the windows a few weeks later and the fitting of the lift set to begin early summer 2026.

The new lift shaft during construction. Image: JT Mackley
The new lift shaft during construction. Image: JT Mackley

Cost control

The biggest challenge on the project, say Hone, has been “controlling the costs. We are in that place, as a local authority, where we just don’t have the luxury of throwing more money at it.”

There have been some savings on the job. For instance, Mackley proposed an off-the-shelf kerb rather than a heritage one, which come with a lower capital cost and a lower maintenance cost.

However, there will be some difficult conversations to come. “We are currently assessing the variations associated with the contract at this time,” says Graham.

Even more of a vexing problem is how the restoration of the remaining arches, and associated access, will be funded. This is a matter which comes in part under the remit of the newly formed Seafront Development Board, a group of private and public sector professionals developing a vision for the seafront which includes ways to attract much needed investment.

The many discoveries and lessons from Phase One will reduce some risks and drive some efficiencies on future phases. And this first section, when completed, will demonstrate the value of this heritage structure to Brighton & Hove, and beyond.