News

Construction Manager of the Year Awards 2020: Healthcare

Image credit: Adam Davies

  • Gold winner: Matt Gavin MCIOB
  • Kier Construction
  • Project: MRI Building, University Hospital of Wales, Cardiff
  • Scope: Construction of six-storey MRI building, completed in 96 weeks
  • Client: Cardiff and Vale University Health Board
  • Contract: NEC option C
  • Value: £12m

For this six-storey replacement MRI facility at the biggest hospital in Wales, Matt Gavin had to deliver the new-build project in an enclosed courtyard, surrounded on all sides by live medical facilities.

His logistical planning included erecting a tower crane inside the courtyard, the only practicable way to move materials into and out of the site. In an emergency corridor over which the crane lifts would take place, he installed a CCTV camera linked to the crane cab so the operator could check if the corridor was clear before each lift.

Register for free or sign in to continue reading

This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.

Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.

Story for CM? Get in touch via email: [email protected]