Legal

SSE v Hochtief: lessons on NEC contract interpretation

Story for CM? Get in touch via email: [email protected]

Comments

  1. Thanks Sarah,

    Very interesting argument put from both parties, and felt compelled give my comments.

    Irrespective of Hochtief having accepted design and having knowledge of the defect and risks, how the design was implementation is still predicated on the design, hence they bear certain liability under the contact. However Hochtief were hard done by SSE under such terms set out in the contract, and SSE should bear some liability under clause 81 of the NEC 2 contract. Stipulating such liability at the contractor’s risk may be subject to interpretation as existing defects can be attributed to a certain risks, and as such should not have to be borne by the contractor only but as well as the client, SSE in this case.

  2. Sarah well done. Very much a landmark pointer you have shown us all

Comments are closed.

Latest articles in Legal