The impact of covid-19 on construction works has brought the role of the programme into sharp focus.
It is
imperative that contractors successfully plan and programme their way through social
distancing and coronavirus constraints. Ensuring the works maintain
productivity and reduce delay and disruption will be critical to success. Low
margins already impair the sector, and covid-19 measures will likely make
matters worse.
The new governmental
and Construction Leadership Council’s Site Operating Procedures for covid-19
workforce protection should be commended. Nonetheless, while positive for the
workforce, the time and monetary impact of implementing will be significant.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
The site planner
and wider team must consider many constraining factors for the operation of site
works. These include consideration of slow remobilisation due to factors such
as:
- Ill health
- Furloughing or an unwillingness to return until
the pandemic subsides
- Materials held up in ports
- Supplier insolvency.
All the
above, and potentially other factors will present further unquantifiable risk
and uncertainty to the programme.
The most
immediate issue is likely to be the social distancing of site activities.
Construction is by nature ‘gang’ related. Small teams work together for the greater
good of increased productivity. Where a hod-carrier can no longer place bricks
adjacent the bricklayer, or the steelfixer must keep a distance from the
shuttering joiner, productivity will undoubtedly fall.
Anecdotal
evidence suggests that productivity has reduced by between 25% to 75% on sites
reopening since lockdown. Productivity will likely rise from these levels,
albeit slowly. The industry is adept at overcoming challenges. Nonetheless, a lasting
fall in output should be expected.
Sector impact will vary. Civil works perhaps less so as plant is often controlled by a single operator in the open environment. Internal building trades will likely suffer the largest impact. Mechanical, electrical and fit out trades often work in close proximity within a closed environment. High rise construction will be affected by fewer operatives allowed into hoists and lifts.
Impact on
project planners
How do
project planners plan for this ‘new normal’? Standard output rates for the
productivity of trades will no longer apply. No ‘time and motion’ work studies
exist for social distancing of covid-19. In addition, the programme is likely
to be particularly sensitive to changes in the critical path.
Before lockdown,
site management would have had a reasonable view of the current and future
critical paths. Factoring in furloughed designers, insolvent suppliers and
unavailable materials creates uncertainty and change. It is expected that the
critical path will shift often between remaining, design, procurement and
installation.
Adjusting to
this change will require the project planner to maintain regular updates of the
programme.
Where
required, these should be issued contemporaneously to the client, ideally
weekly or as a minimum, monthly. Incidences of disagreement over contractor’s
notices of delay have already been observed. The party receiving the notice
considers the site open and continuing with minimal impact. The contractor,
closer to the loss of productivity, has a different view. The likelihood for
disputes is large.
Daily labour
records recording key activities are critical. They should identify:
- What the workforce are doing
- Where they are working
- What is achieved and cannot be achieved.
Detailed
record keeping practices have fallen by the wayside over the years. The current
crisis brings the need for good records to the fore. Record keeping should be viewed
as a dispute avoidance measure rather than a claims practice.
Some evidence
suggests employers recognise preliminaries costs will rise to include for extra
site accommodation, hoists and site logistic measures. But development budgets
will force contractors into new ways of operating. The Construction Leadership
Council recently issued its ‘Roadmap to Recovery’. New approaches are called
for in compensating for the loss of productivity arising from the pandemic. These
include offsite manufacturing and further digitisation.
The role of
the project planner in this ‘new normal’ will be key. Recording changes in
productivity and emerging programme risks will factor large. However, the wider
role will be in scenario planning and providing alternatives to overcome the
challenges of the pandemic.
Tom Francis is a director at Decipher and current chair of the CIOB Manchester Hub