NEC4 X22: more contractor incentive in two-stage contracts?

Story for CM? Get in touch via email: [email protected]

Comments

  1. My understanding which is different to the client is as follows.
    We have overspent on ECi (stage 1) no pain or gain
    We have now priced stage two which is cost to date for stage 1 plus the target figure for Stage 2. This gives a revised total target figure for the whole project. Which will be subject to pain or gain.

    Clients understanding is Stage 1 and 2 are separate and subject to there own target figures and Pain or Gain. So it is critical to make sure we have CEs in place to cover the over spend at ECI. To reduce the pain.

    What I’m mainly after is the revised target cost to date (including fee) plus revised target for stage 2?